January 2026 Progress Update

#construction#progress#update

Construction continues at a strong pace as we work toward completing several key milestones by the end of January 2026.

Alhamdulillah, construction on our community center continues to progress well. Here is the latest update on where we stand and what lies ahead.

In Progress

The following work is currently underway and expected to be completed by or before January 31, 2026:

Stud Framing

  • Main floor framing has been completed
  • Work is set to begin on the second floor

Stud framing progressStud framing progress

Mechanical & Electrical

  • Electrical rough-in is in progress
  • Plumbing rough-in is in progress

Sprinkler System

  • Installation is approximately 60% complete

HVAC Ductwork

  • Installation is approximately 95% complete

Remaining Work

After the current phase is complete, the following work remains:

  • Drywalls
  • Electrical fixtures
  • Plumbing fixtures
  • Flooring
  • Parking lot
  • Exterior lighting

Thank You

We are grateful for the continued support of our community. Every donation and dua brings us closer to opening the doors of this facility for the benefit of all.

Stay tuned for more updates as we approach the finishing stages of construction. May Allah bless this project and all who contribute to it.