
ConstructionJune 3, 2026
June 2026 Progress Update
#construction#progress#update
HVAC and ducting are complete, main floor rough-in is finished, and the elevator is approximately 90% installed.
Alhamdulillah, we are pleased to share another round of meaningful progress on our community center. Several major milestones have been reached since our last update.
Completed
HVAC & Ducting
- Heating, ventilation, and air conditioning systems are fully installed
- All ductwork throughout the building is complete
Main Floor Rough-In
- Electrical, plumbing, and mechanical rough-in on the main floor are complete
- The main floor is ready to move into the next phase of finishing work
In Progress
Second Floor Rough-In
- Work has now shifted upstairs
- Electrical, plumbing, and mechanical rough-in on the second floor is underway
Elevator
- Installation is approximately 90% complete
- Final commissioning and testing to follow shortly
Thank You
We are deeply grateful for the continued support, generosity, and duas of our community. Every contribution brings us closer to opening the doors of this facility insha'Allah.
Stay tuned for more updates as we continue toward the finishing stages of construction. May Allah accept this effort and make it a source of benefit for all.